First bore of Silvertown Tunnel completes

First bore of Silvertown Tunnel completes

  • New public-transport focused tunnel will reduce congestion and improve reliability and resilience at Blackwall Tunnel

  • 82m-long TBM now being rotated in sections ahead of tunnelling second bore in coming weeks

 Jill, the Tunnel Boring Machine (TBM) delivering the Silvertown Tunnel in east London, has reached the rotation chamber in the Greenwich site, completing the tunnelling of the first bore.

The TBM, named in honour of Jill Viner, the first female bus driver in London, completed its 1.1km (1106m) drive on 15 February 2023. Once open in 2025, the twin-bore 1.4km Silvertown Tunnel will link Newham to the Greenwich Peninsula and provide improved bus links across the Thames. By reducing congestion at the Blackwall Tunnel, providing new cross-river bus links and creating a more reliable river crossing for cars, vans and lorries, it will support economic growth across east and southeast London. The Silvertown Tunnel will also provide better access to new job opportunities and support new housing and business developments across the wider area.

The project is being delivered by the Riverlinx CJV, who are a joint venture contracted by TfL and Riverlinx comprising of three civil engineering and construction companies: BAM Nuttall, Ferrovial Construction and SK ecoplant. The project is being delivered through a design, build, finance, operate and maintain contract, with the vast majority of the funding for the new tunnel is coming from private finance which has been specifically raised for the scheme.

Aside from a small section around the tunnel entrances, which will be built using a ‘cut and cover’ technique, the two bores that make up the Silvertown Tunnel are being built using one 82 metre-long, 11.9 metre-diameter TBM. The TBM averaged around 18 metres a day during the delivery of the first bore as it worked its way under the river from Newham to Greenwich. The conveyor system, built to remove excavated materials, has helped transport around 275,000 tonnes of spoil from the tunnel via barge as well as spoil from the retrieval chamber of the TBM and other civils work within the Newham site.

 

Having arrived at Greenwich, the TBM will now be rotated around in pieces within a 40m rotation chamber, before beginning its 1.1km journey back under the river to the Silvertown site in Newham in the coming months. The process will involve sections of the TBM being placed on ‘nitrogen skates’ within the rotation chamber and turned around before boring the second tunnel. This is a highly innovative and complex process, where the individual sections of the TBM, including the 1200tn cutting shield, will be spun 180 degrees inside a shaft and then reassembled and reconfigured to facilitate tunnelling the second bore back to Newham.

 

Once tunnelling recommences, spoil from the second tunnel will be fed back via the conveyor systems installed within the first tunnel to allow it to also be removed by barge from the Newham site. The second bore is expected to be completed by the end of Summer 2023.

 

Helen Wright, Head of the Silvertown Tunnel programme at Transport for London (TfL), said: "The completion of the first bore of the Silvertown Tunnel is a huge milestone for the project. Work is now underway to rotate the TBM within the rotation chamber, which is an innovative and complex process, so tunnelling the second bore can begin in the coming weeks. We are committed to working hard to ensure that this project is delivered with minimal impact to those living, working and visiting the local area and have extensive monitoring in place to ensure than this continues to be the case during and after construction."

 

Juan Angel Martinez, Project Director at Riverlinx CJV said: “We are extremely proud of the team we have delivering the construction for the Silvertown Tunnel project. The solutions we are implementing are pioneering for the UK market and we continue to be committed to completing the project expertly in the most efficient, sustainable way and to the highest level of safety and quality.”

 

In recent months, significant progress has been made on both sides of the river on the project. Work on the two tunnel portals is progressing well, and piling and concrete pores pours for the foundations for the cut and cover sections of the tunnel, as well as the portal entrances, are also now well underway. Repairs have also been made to the river wall at Newham to ensure they are not affected while tunnelling takes place.

 

Alongside the construction of the tunnel, TfL and Riverlinx are also actively working on the designs for the walking, cycling and landscaping improvements, which will be delivered around either side of the tunnel entrances. These will see new dedicated cycleways and footways, as well as 'shared space' and new public realm installed across Tidal Basin Road roundabout, which will link in with wider improvements planned by Newham Council across the Royal Docks area. The proposed landscaping around the tunnel entrances, as well as a green roof on both tunnel portal buildings, will also form part of the scheme's commitment to environmental improvements and promoting biodiversity across the wider area.

 

Construction has also commenced on the new walking and cycling bridge across the A102, which will replace the existing 1960s footbridge with a new, fully accessible bridge built to modern design standards and improved lighting. The new bridge will provide a safe and easily accessible crossing for those walking and cycling, including those using cargo bikes, on the Greenwich Peninsula and has also considered future neighbouring development proposals. The main span of the new bridge will start to be installed later this Spring, and the existing bridge will be kept in use until the new bridge is fully opened.

 

To follow progress of the TBM as it returns under the Thames, please visit www.riverlinx.co.uk For more information about the Silvertown Tunnel, please visit www.tfl.gov.uk/silvertown-tunnel

 

Notes to editors

  • Throughout the development of the Silvertown Tunnel, the project has been subject to a rigorous and transparent process to demonstrate it is the right solution and that its impacts have been properly assessed and mitigated.

  • All vehicles working or delivering to the construction sites meet Euro VI standard and Riverlinx have adopted a Stage IV or better policy for Non-Road-Mobile Machinery (NRMM) across the project, including using innovative hybrid technology. This means that they meet or exceed the requirements of the GLA's NRMM Low Emission Zone. All construction vehicles will also comply with the latest safety standards in support of our Vision Zero ambitions.

  • Once the Silvertown Tunnel is open, the total number of buses running through both Blackwall and Silvertown Tunnels will increase, with TfL committed to running at least 20 zero-emission buses per hour through the tunnels at peak times. For more information on TfL's recent consultation (which closed on 11 January 2023), please visit https://haveyoursay.tfl.gov.uk/silvertown-tunnel-bus-network

  • TfL expects the overall provision of buses through the area could further increase to 37 buses per hour over time as new developments, including at the Royal Docks and Greenwich Peninsula, are completed during the next decade.

  • User charging at the Blackwall and Silvertown Tunnels, which will commence once the Silvertown Tunnel is complete, alongside the new zero-emission bus network, will help to manage traffic levels and encourage people to switch their journeys to public transport where possible. No user charges have been finalised yet and any times and costs within the submission are indicative to allow for approval to be obtained. The final charges will be announced ahead of the Silvertown Tunnel opening in 2025 once further modelling, including assessments on concessions, are complete.

  • TfL is legally committed to delivering a wide range of improvements and measures to reduce the impact of the new tunnel and support the wider local area. These include:

o   £1m worth of support for local businesses to help them adapt to the user charge when the Silvertown Tunnel is operational. This could include helping businesses with staff travel planning or funding potential infrastructure such as cycle racks and electric vehicle charging points

o   A user-charging discount to specifically help low-income residents in the host boroughs of Greenwich, Newham and Tower Hamlets. This could look similar to the existing TfL Bus & Tram Travelcard which offers a 50 per cent discount on public transport for those who receive certain state benefits.

o   £2m in bus concessions for local residents to help promote the new cross-river bus services which will run through the tunnel, as well as supporting them to move away from unnecessary private car use. TfL will also enhance river crossing facilities for cyclists and pedestrians across the local area

  • Both the tunnel and the surrounding area also fall within the Ultra Low Emission Zone, and since December 2020, TfL has undertaken a comprehensive programme of air quality monitoring to ensure the impacts of the Silvertown Tunnel are fully understood, and to support the delivery of the overall air quality improvement expected as a result of the scheme. 38 diffusion tubes and three continuous monitoring stations recording nitrogen dioxide (NO2) levels have been installed across five boroughs, and TfL has also installed a continuous PM2.5 monitor in Newham, to complement existing local authority monitoring within Greenwich and Tower Hamlets.

  • Data collected from the continuous monitoring stations is available on the London Air Quality Network (https://www.londonair.org.uk/) and support wider AQ initiatives across the capital. Air quality updates are also provided via the Silvertown Tunnel Implementation Group, with TfL's first report on air quality monitoring available to view here: https://tfl.gov.uk/cdn/static/cms/documents/silvertown-baseline-aq-monitoring-report-2021.pdf



Previous
Previous

Blackwall Tunnel closed southbound weekend of 31 March to 3 April for installation of new walking and cycling footbridge in Greenwich

Next
Next

Riverlinx wins Innovation in Design award for Silvertown Tunnel project