Planned Traffic Management – A102 (Blackwall Tunnel)
Enabling works on the central reservation of the A102 will start on 17 October as part of the phased construction of the new carriageway tie in. One lane will be closed in either direction during a two-week period until 31 October. Upon completion of these works, the A102 southbound will be reduced from three lanes to two between Boord Street and the off slip to Blackwall Lane, which will also be reduced to one lane until Summer 2023. The northbound carriageway will return to full capacity during this period.
The start of these works has been timed to tie in with the October school holidays, when traffic levels are usually lower.